A how-to guide to installing Firestone RubberCover EPDM membrane onto tiles.
Step 1
Allow 150mm overhang onto tiles.
Step 2
Dress lead into place 6” onto tiles, 3” onto the deck. We recommend using minimum 9” Code 4 lead cut into 1200mm lengths max.
Step 3
Fix into position using screws.
Step 4
Apply Quick Prime plus to lead and rubber approx. 160mm wide using Quickscrubber pad and handle. Allow to go touch dry.
Step 5
Centralize the 6" batten cover strip and carefully remove release paper applying downward pressure. Use silicone roller to seal.