Onto Tiles Download PDF

A how-to guide to installing Firestone RubberCover EPDM membrane onto tiles.

Step 1

Allow 150mm overhang onto tiles.

Step 2

Dress lead into place 6” onto tiles, 3” onto the deck. We recommend using minimum 9” Code 4 lead cut into 1200mm lengths max.

Step 3

Fix into position using screws.

Step 4

Apply Quick Prime plus to lead and rubber approx. 160mm wide using Quickscrubber pad and handle. Allow to go touch dry.

Step 5

Centralize the 6" batten cover strip and carefully remove release paper applying downward pressure. Use silicone roller to seal.